OLD STAGECOACH ROAD - CENTER STREET
Limits on the 3 segments that will be constructed independently to accelerate delivery:
Old Stagecoach Road North: From Six Creeks Boulevard to Veterans Drive, with a new roundabout constructed at the Six Creeks Boulevard intersection.
Old Stagecoach Road: From Center Street to Six Creeks Boulevard
Center Street: From Veterans Drive to Old Stagecoach Road, with a new roundabout constructed at the Old Stagecoach Road intersection.
Project Updates
Summer 2026
Old Stagecoach Road - Final Design
The project has advanced into final design development following approval of the plans on June 22, 2026. Construction is expected to begin in Fall 2026.
Center Street (Off-system) - Construction
Construction is moving forward on this project. The contractor received the signed contract in May, the Notice to Proceed has been issued and utility relocation work is expected to begin in Summer 2026.
Old Stagecoach Road North - Final Design
The final design plans (100% PS&E) are under review. In addition, all right-of-way is expected to be complete by Summer 2026.
Overview
The City of Kyle is improving a 2.2-mile stretch of Old Stagecoach Road North, Old Stagecoach Road, and Center Street to reduce traffic congestion, enhance safety, and improve traffic flow. Funded by the 2022 Road Bond, the project focuses on roadway widening and reconstruction from Veterans Drive (RM 150) along Old Stagecoach Road North and Old Stagecoach Road. Old Stagecoach Road North will become a four-lane roadway, while Old Stagecoach Road will be widened to three lanes. On Center Street, the existing three-lane section will be improved by widening the center lane to enhance operations. To accelerate delivery, all three segments of the project will be bid and constructed independently.
-
Old Stagecoach Road North
Length: 0.50 miles
Location: Six Creeks Boulevard to Veterans Drive (RM 150)
Old Stagecoach Road
Length: 1.02 miles
Location: Center Street to Six Creeks Boulevard
Center Street (West Segment)
Length: 0.62 miles
Location: Old Stagecoach Road to Veterans Drive (RM 150)
-
Old Stagecoach Road North
4-lane reconstruction and widening
Old Stagecoach Road
Expand roadway to one lane in each direction with a middle left turn lane
Center Street (West Segment)
Expand roadway to one lane in each direction with a middle left turn lane
-
Construction funded by the City of Kyle’s 2022 Road Bond
Total Project Cost = $41.2 M
-
Kyle City Council opted to bid all three segments independently to accelerate delivery.
Old Stagecoach Road North
Construction: Fall 2026
Old Stagecoach Road
Construction: Fall 2026 - Winter 2028
Center Street (Off-system)
Construction: Summer 2026
Schedule and Project Status
Project Resources
-
Click on the title below to view each segment.
-
Click on the title below to view each item.
-
Click on the title below to view each item.
-
Looking for detailed information about the Old Stagecoach Heritage Live Oak?
Visit our dedicated Old Stagecoach Heritage Live Oak Tree page. -
Click on the title below to view:
Old Stagecoach Road & Center Street (off-system) Preliminary Engineering Report (PER)
-
Click on the title to view each item: